- Project is currently in a Winter Shut Down.
- No on site work is expected until Spring 2013 when the landscape restoration and final pavement markings will be re-evaluated.
Author Archives: admin
Winter Update 1/9/2013
Posted in Uncategorized
Work for the Week of 11/26/2012
- Final sewer line cleaning.
- Traffic signal timing and programming.
- Traffic signal maintenance transfer.
Posted in Uncategorized
Work for the Week of 11/19/2012
- Final project work on pavement and curb.
- Testing of Emergency Vehicle Detectors.
- Sealing of longitudinal pavement joints.
- Sealing of lateral curb joints.
Posted in Uncategorized
TRAFFIC ALERT: SPEED LIMIT INCREASE
Be advised that the speed limit on Orchard Road between US 30 and Jericho will increase from 35 MPH to 45 MPH today.
Workers will still be on site over the next few weeks to complete some final work items.
So please watch for workers, obey the new speed limit and stay off your cell phones while driving through the job site.
Thank you for your patience and cooperation.
Posted in Uncategorized
Work for the Week of 11/12/2012
- Final General Site Clean-Up
- Installation of new 45 MPH speed limit signs.
Posted in Uncategorized
Work for the Week of 11/05/2012
- Sewer Manhole repairs at Orchard and Brentwood.
- Activation of the Roadway Lighting at Aucutt.
- Landscaping seed and blanket in the Jericho Basin and Aucutt Basin.
- Final General Site Clean-Up.
Posted in Uncategorized
Work for the Week of 10/29/2012
- Fine grading of the topsoil on the west parkway.
- Removal of the temporary wood poles for the traffic signals.
- Landscaping seed and blanket throughout the site weather permitting.
Posted in Uncategorized
Work for the Week of 10/22/2012
- Installation of Aggregate Shoulder along the Orchard bikepath.
- Placing topsoil along the west parkway.
- Activation of the new traffic signal at Rochester (Thursday).
- Landscaping seed and blanket throughout the site weather permitting.
Posted in Uncategorized